Expert, flexible training in the use of the most powerful scheduling software program in the world: Primavera P6 by Oracle. Call today! (916) 779-4145
Primavera Scheduling

All posts tagged WBS Summary

My Least Favorite Activity Type

Categories: Activity Types, Level of Effort, P6 EPPM, P6 Professional, WBS Summary
Comments Off on My Least Favorite Activity Type

Primavera SchedulingWhile I consider my self pretty adventurous when it comes to Primavera P6, I admittedly have little use for one particular activity type, the WBS Summary. To review, the WBS Summary calculates its Start and Finish date (and therefore, duration) from all other activities that have the same WBS code. On the surface, this seems like a great idea because logic is not required. The WBS Summary is the only activity type in Primavera P6 that works sans logic. And this is what I do not like about it.

I always check the Schedule Log before I publish a schedule. As you should know, the Schedule Log has a topic called “Warnings” that discusses, among other concerns, the number of activities that are missing predecessors or successors. The correct number of “open ends” would of course be two; the first activity will not have a predecessor and the last one will not have a successor. No other answer is acceptable. Owners will also be checking the Schedule Logs during their reviews. Open ends are an easy way to get a schedule rejected.

Because the WBS Summary does not want or need logic, it creates what appears to be a de facto mistake in the schedule. If the person reviewing the schedule figures out that the open ends are due to this particular activity type, then perhaps they would accept the schedule regardless. But it has been my experience that owners do not want to hear any excuses as to why some activities have logic and others do not. Open ends are an unnecessary distraction from other items (sequences, durations, coding, etc.) that need to be checked.

It is possible to add relationships to a WBS Summary to make the open ends disappear, but this basically defeats the purpose of having them in the schedule in the first place. Why not use the Level of Effort instead? The Level of Effort also calculates its dates and duration automatically, but requires logic. Therefore, the Level of Effort does not create any concerns in the Schedule Log. Both of these activity types can also have resources assigned, so nothing is lost by switching to the Level of Effort.

Logic can be added to a WBS Summary without affecting the way it calculates its dates and duration, but again, why not use the Level of Effort instead? While they may seem interchangeable, the Level of Effort demands logic, and therefore forces us to add proper relationships. The WBS Summary is a little too accommodating. I want my activity types to enforce good habits!

Better still, the Level of Effort can transcend more than one WBS code which makes it far more flexible than the WBS summary. If I really need to see the dates and durations for WBS codes I can Group by WBS and choose to Show Group Totals. This saves me the trouble of adding a bunch of WBS Summary activities to my schedule for no other purpose than seeing summary dates and durations.

In the screenshot below, the WBS Summary activity is purple. Yes, this activity tells me the Foundations start on May 17 and finish on June 28, 2016 and have an overall duration of 30 days. Yet the same information appears in the Group Totals:

Primavera Scheduling
So there is no additional benefit to adding the WBS Summary activity if the only information being provided are the summary dates and duration.

I know some users are adding WBS Summary activities as a simplified way of cost loading a schedule from the top down. They put all of the costs in the WBS Summary activities rather than the actual work tasks. But Primavera P6 has a tool called Top Down Estimation that is better suited for that purpose. While it is possible to specify a non-linear distribution curve for resources, the reality is that you are still treating every day as having the same value. That is simply unrealistic.

A Primavera P6 compatriot did mention to me a reason why he uses the WBS Summary activity on a temporary basis. When Microsoft Project schedules are imported into Primavera P6, the summary bars are imported as activities. He uses the Microsoft Project summaries as temporary placeholders for checking logic and durations. Similarly, I will use the descriptions of the Microsoft Project summary activities to build my WBS codes before deleting these superfluous tasks,